Featured Images
Question 1
A photo shows  service-entrance conductors going through to a second disconnect. Is this a code violation?

Question 2
Is there a section in the 2002 NEC that states the number of meter bases allowed on a single residence?

Question 3
A violation of 230.72?

Question 4
Softit question: Doesn't 230.9(A) only apply to open conductors or multiconductors without an overall jacket?

Question 5
What are 225.30 and 230.2 trying to accomplish from a safety perspective?

Question 6
Can you tell me what year the NEC started requiring GFCI protection for equipment as per 230.95?

Question 7
What actually is a “readily accessible location”?
 
 
 
IAEI News>Focus on the Code >CMP-4
Focus on the Code Questions for CMP-4
The Focus on the Code column is intended to assist our readers and members in understanding the requirements of the National Electrical Code. Our Code consultants consists of IAEI representatives on the CMP-4 panels of the NEC and other selected experts. 


Question 1. I have a situation (see figure 1) that I believe is a violation of 230.7, which states that conductors other than service-entrance conductors are not allowed in the same raceway. The attachment shows the service-entrance conductors going through to a second disconnect. The person I am discussing this with said that this would only be a violation if the disconnect were considered a raceway. When reading the definition of raceway, I understood that this panel would contain busbars and would be considered a raceway. To me it would easily allow the overcurrent protection of the first disconnect to be bypassed if a fault occurred. I will never allow this to happen in my jurisdiction, but could I get an interpretation anyway. — D. K.

Answer 1. As it is drawn in the PowerPoint slide provided, there would be no violation of 230.7 as the separation requirements of this section are specific to the space within service raceways and cables. The space provided for conductors within a disconnect enclosure is typically considered as gutter space rather than a raceway. As it is described in Article 100, for the enclosure to be considered a raceway it would have to be used expressly for holding wires, cables or busbars. The enclosure in the slide also contains an overcurrent device. Enclosures containing overcurrent devices are included in the scope of Article 312. Specifically, 312.8 permits the space within the enclosure for an overcurrent device to be used as a junction box, auxiliary gutter or raceway for conductors feeding through or tapping off to other overcurrent devices, provided there is adequate space for the purpose. Additionally, the conductors cannot fill the space, at any cross-sectional area, to more than 40 percent, and any splices cannot fill the space, at any cross-sectional area, to more than 75 percent. Where adequate space has been provided, it is common to see service-entrance conductors supplying panelboards or service equipment with main disconnects that are run in the same space with, or alongside of, feeders or branch circuits within the panelboard enclosure. Although 312.8 permits the space to be used "as a raceway" (to hold the wires), it does not require it be treated "as a raceway." The space referred to in the question is not considered as a raceway for the purposes of applying 230.7. — Mark Hilbert, CMP-4

| Return to top |


Question 2. Is there a section in the 2002 NEC that states the number of meter bases allowed on a single residence? — J. J.

Answer 2. The National Electrical Code is silent concerning the number of meters allowed on a single family dwelling, or any building or structure for that matter. Typically, a single-family dwelling will have one supply (service or feeder) with one meter. However, if the local utility has different rate options available, there may be an additional meter for electric space or water heating, etc. Articles 225 and 230 contain many requirements related to services, feeders or branch-circuits supplying buildings or structures and the number and location of the disconnecting means for those supplies. Both articles are silent on the number of meters allowed. Where the supply to a building or structure is metered, it is likely that those providing the metering service will have specific requirements related to the number and location of meters. — Mark Hilbert, CMP-4

| Return to top |


Question 3. This building is fed by two 4" service laterals connected together at the supply end. (Section 230.2 would consider this a single service.) Of the two exterior disconnects, one feeds the upper level and one feeds the basement of this single structure multiple occupancy building. The two interior panels and one disconnect feed the main level. Photo 1  | Photo 2 Is this a violation of 230.72? Assuming it is not, would it be if it were being fed by one lateral? — R. T.

Answer 3. In order to properly answer your questions, they will be presented in the order in which they were asked. However, prior to that, I will describe your photographs as I understand them to be certain that we are all looking at the same installation. Photo 1 displays the two 4" conduits that you describe as the two service laterals in question. One conduit enters the bottom of a wireway; and on the top of that wireway, there are two meter sockets and two weatherproof disconnects. The second conduit enters the bottom of what appears to be a CT cabinet; and attached to that is a meter socket and a conduit that enters the building through an LB fitting. Photo 2 is an interior photo displaying two panelboards, one interior disconnect switch, and two conduits entering the building. Based upon your questions and photos 1 and 2, I am going to draw the following conclusions:

1. The conductors contained in the 4" conduits are a minimum size of 1/0.2. The interior disconnect switch is supplied through the conduit that enters the building from the CT cabinet.3. The two interior panelboards are attached directly into the back of the CT cabinet and the panelboards contain main circuit breakers.4. The main level that is fed from the two interior panelboards and one interior disconnect is one occupancy.

Prior to answering your two questions, we should also review your opening statement relative to this installation meeting the requirements of Section 230.2 of NEC-2005. The first item to review in attempting to apply this requirement is the specific reference to Section 230.40, Exception No. 2. This is a mandatory reference and the application of more than one lateral connected at the supply end and not connected at the load end cannot be utilized unless the requirements found in 230.40 are met. The primary requirement of Section 230.40 is that each service drop or lateral to a building shall supply only one set of service-entrance conductors. There are five exceptions to this rule and, as specified above, we are interested in Exception No. 2 which states, "Where two to six service disconnecting means in separate enclosures are grouped at one location and supply separate loads from one service drop or lateral, one set of service-entrance conductors shall be permitted to supply each or several such service equipment enclosures." In looking at how it relates to the installation you have described, I do not believe the exception can be applied due to the fact that the disconnecting means are not "grouped at one location."Your first question is in reference to the installation complying with NEC Section 230.72. This section states, "the two to six disconnects as permitted in 230.71 shall be grouped. Each disconnect shall be marked to indicate the load served." As you can see, this section refers to disconnects permitted in Section 230.71(A), which states:"(A) General. The service disconnecting means for each service permitted by 230.2, or for each set of service-entrance conductors permitted by 230.40, Exception Nos. 1, 3, 4, or 5, shall consist of not more than six switches or sets of circuit breakers, or a combination of not more than six switches and sets of circuit breakers, mounted in a single enclosure, in a group of separate enclosures, or in or on a switchboard. There shall be not more than six sets of disconnects per service grouped in any one location. For the purpose of this section, disconnecting means used solely for power monitoring equipment, transient voltage surge suppressors, or the control circuit of the ground-fault protection system or power-operable service disconnecting means, installed as part of the listed equipment, shall not be considered a service disconnecting means."It is interesting to note here that when 230.71 references the exceptions to Section 230.40, Exception No. 2 is specifically eliminated. For that reason the installation is in violation of 230.72.

When examining or specifying a service installation, you cannot choose to use one exception for one portion of the installation and a separate exception or main rule allowance for another portion of the installation.Your second question asks whether or not having three disconnects grouped inside and two grouped outside, and all being fed from one lateral, would be an installation that was in compliance with Section 230.72. For this, you would be once again referred to Section 230.71 and the straight answer would be no, unless the installation met one of the exception criteria defined in Section 230.40, Exceptions 1, 3, 4 or 5. Of these, Exception No. 1 — which reads as follows, "A building shall be permitted to have one set of service-entrance conductors for each service, as defined in 230.2, run to each occupancy or group of occupancies" — is the only one that could be considered for this particular installation. This would be a local enforcement decision as to whether the two exterior sets of service-entrance conductors and disconnects qualified as one group of occupancies and the three interior sets of service-entrance conductors and disconnects qualified as an additional occupancy, or a second group of occupancies if there were actually more than one.

This, of course, would be dependant on your statement that there would be only one service lateral, not the two that you show in your photographs. I have reviewed the original proposals for the 230.40 language and it is my opinion that the language was not written for an installation such as this; however, the written language as it is, could be interpreted this way. The other very real concern relative to an installation such as this would be disconnect location information during an emergency situation. During the NEC-2005 cycle, the panel did closely examine language on the requirement for labeling the location of all disconnecting means at each disconnecting means when utilizing the exceptions to 230.40 for the concerns of safety when someone was attempting to remove power from the building in an emergency situation or a maintenance situation. I am quite certain that this requirement will be reviewed once again in the 2008 NEC cycle. — James Rogers, CMP-4

| Return to top |


Question 4. I recently installed a 300-amp service upgrade at a residence in North Arlington, New Jersey. The residence is a three-family dwelling, plus I added a house panel and meter. We installed a trough outside on the house and ran a 3-inch pvc schedule 80 from the trough up the house vertically to the service head. The top of the service head is equal to the top level of the upper window (the upper part of the window that is not generally used). The pipe is less than 3 feet from the window. The electrical inspector wants the head to be  totally above the upper part of the window by 1 inch. We cannot go any higher because the soffit is in the way. He claims that according to 230.9(A) we cannot keep this installation the way it is. Now upon reading 230.9(A), doesn’t this only apply to open conductors or multiconductors without an overall jacket? Or are the wires considered to be open conductors when they are coming out of the service head and that is what needs to be 1 inch above the window [using the exception to the rule below 230.9(a)]? — R. M.

Answer 4. I will answer your question with the information that you have supplied and also offer some other information relative to the installation as you have described it. First of all, I am assuming that all parties are working from NEC-2002. In your explanation you describe a service installation in rigid nonmetallic conduit with the individual service conductors exiting the conduit through a weatherhead at the top of the conduit. In reviewing your diagram, this would place the exposed service conductors adjacent to the window in an area where 230.9(A) prohibits such conductors. In this or any other similar installation it is the conductor that must be above the window if you were to apply the exception to 230.9(A), not the raceway or the weatherhead. You are correct when you imply that the raceway could be run directly adjacent to the window as long as the conductors are not exposed in that area.The next consideration for this installation would be the location of the service-drop conductors and their attachment point on the building.

The height and clearance requirements of Sections 230.24 and 230.26 would have to be met as well as the proximity to the weatherhead requirements of 230.54(C). There is an exception to 230.54(C) that could be applied to this installation.The last area of concern for this installation is the wireway (trough) installation that you describe. The first consideration would be the proper sizing, based upon calculated load, of both the main conductors and the conductors supplying the individual disconnects. These conductors are service-entrance conductors by the definition of such in Article 100. To splice or tap these conductors would be allowed by Section 230.46 provided properly listed or approved connectors were utilized and the conductors and splices met the requirements of 300.13 and 300.15. Although not specifically referenced here, the fill requirements for conductors and splices in wireways found in Article 376 for metal wireways and Article 378 for nonmetallic wireways would also have to be complied with. Should a metal wireway be utilized, the proper grounding and bonding requirements would have to be met. I hope that this answers your questions relative to this installation; please feel free to contact me should you require further clarification. — James J Rogers, CMP-4

| Return to top |


Question 5. I have two questions. The first question is about NEC 225.30 and 230.2, which both refer to power supplies to a building or structure. Would you please explain exactly what the rules are trying to accomplish from a safety perspective?

The second question is about fire walls. The NEC definition of a building explains that it is a structure that stands alone or is cut off from adjoining structures by a fire wall. Can a fire wall be anything other than what the International Building Code defines as a fire wall? — K. M.

Answer 5. You have asked for a description of potential safety issues relative to the main rule requirement in Sections 225.30 and 230.2 for allowing only one source of electrical power to enter a building.

The first and foremost concern for both requirements is the ability of personnel who are responding to a public safety hazard, such as but not limited to a fire, to be certain that they are eliminating all power to a building when a decision is made to do so. To accomplish this, there is not only the main rule requirement for one source of power to a building as you have referenced, but there are also requirements found in Section 230.2(E) for the proper identification by means of a permanent plaque or directory at each disconnecting means for each source of power entering a building. You will also see here a reference back to Section 225.37 where the same requirements for the proper identification of feeders or branch circuits are located.

The other concerns with multiple supplies are more of a technical concern; however, they could relate back to safety concerns relative to shock and or fire hazards. These hazards could occur throughout a building whenever someone was exposed to circuits from different systems. There could be a shock potential between grounded conductors of the different systems; and if intersystem bonding was not properly performed, there could be a potential difference on grounding conductors and any non-current carrying metal objects that the grounding conductors were exposed to either intentionally or unintentionally. There were changes in both Articles 210 and 215 in this code cycle relative to proper identification of all system branch circuits or feeders within a building at the distribution equipment supplying the systems.

Your second question refers to the building code and I cannot render an opinion relative to this. I can state that Article 100, under the definition of building, refers to the term fire wall. To that extent, fire wall can be differentiated from fire rated construction. I have included below the definition of fire wall as found in NFPA 5000 and the appendices reference contained with the definition.

“Fire Wall. A wall separating buildings or subdividing a building to prevent the spread of fire and having a fire resistance rating and structural stability.

“A.3.3.566.4 Fire Wall. Portions of structures that are subdivided by fire walls are permitted to be considered separate buildings for the purpose of applying this code. The intent of the definition is that fire walls have sufficient structural stability to maintain the integrity of the wall in the event of the collapse of the building construction on either side of the wall.”

In addition, NFPA 221 is the standard that addresses the different types and construction methods of fire walls. Beyond this, it becomes a local issue depending on which model building your city, town, or state adopts for enforcement.

I hope that this adequately answers your questions. Please feel free to contact us for further information on this or any other issue. — James J. Rogers, CMP-4

| Return to top |


Question 6. I am currently on a job that has a 1600-amp, 3-phase, 480-volt service. The generator transfer switch does not have GFCI protection but the main distribution panel does. Can you tell me what year the NEC started requiring GFCI protection for equipment as per 230.95?

The engineer does not want the GFCI on the main distribution with the GFCI protection we are going to add at the generator transfer switch to make it code-compliant. Is there anything the downstream device must have, like a trip setting at a lower value, which would prevent this from being a compliant installation? The AHJ for this area is not strong in the electrical field; he wears a hat for all trades and makes all inspections for all crafts.

Any help would be greatly appreciated.— S.D.

Answer 6. To begin with, one important note that must be clarified is that you are dealing with GFPE or ground-fault protection of equipment and not with GFCI, ground-fault circuit interrupter. As indicated by their names, GFPE deals with protecting equipment from catastrophic failure due to a fault to ground; and the GFCI provides circuit protection for personnel from the hazards of electric shock.

To answer your question relative to when GFPE for service equipment first appeared as a NEC requirement, 230-95 first appeared in the 1971 edition of the Code. It was contemplated by the code-making panel for the 1968 edition; but in the final vote, it was held for further technical comment. Prior to giving you a comprehensive answer, some other information would be necessary, such as what type of facility is being supplied. If this installation is at a health care facility, the answer may be different. How is the generator connected to the system? Does it feed into the main service and supply the entire building, or does it connect on the load side of the service disconnect and supply only limited loads?

I will begin with an answer for a non-healthcare facility where the entire service is supplied by the generator. In that case, then there would be no requirement for a second level of GFPE on the generator feeder as the protection is already provided in the service distribution equipment as you have described it. If the generator supplies selective loads in conjunction with a normal power feeder that is supplied from the service distribution equipment on the load side of the service GFPE, then the allowance of not requiring GFPE found in 215.10 Exception No. 3 would take precedence and, again, no GFPE would be required on the generator feeder. There is a reference to this type of installation found in 230.95 FPN No. 3 whereby it is noted that some type of interconnecting device may be required to assure that the service GFPE device will work in conjunction with the alternate power source. The technical information for an installation such as this would have to come from the manufacturers of the GFPE device and the generator transfer equipment.

You also ask a question relative to downstream protection at a lower rating. The issue of selective coordination of GFPE devices is addressed in 517.17(A), as referenced in 230.95 FPN No. 4. There is no mention in your question that the installation you have described is in a health care facility; however, if it were, then all of the requirements of 517.17 would have to be applied. NEC 517.17(B) specifically addresses generator supplies to essential electrical systems and contains specific language as to when GFPE cannot be applied to these feeders.

I hope that this has adequately answered your question. Should you need further assistance, please feel to contact me. You should also note that a great deal of technical information relative to GFPE devices is on the web sites of the companies that manufacture these devices.
— James J. Rogers, CMP-4
(March/April 2007)

| Return to top |


Question 7. I would like to ask for your interpretation of the following situation. Our office was recently written up by a new electrical inspector for an issue he perceives to be a violation of NEC 230.70(1), but which our office feels to be ambiguous because of the difficulty in determining what actually is a “readily accessible location” since the Code establishes the interpretation is at the discretion of the inspector.

The installation transpired as follows.We had an existing building that was to be divided electrically between two tenants. An existing electrical room that housed an 800-amp service with a CT/Term can, telephone board, house panel and fire protection riser.

 All electrical service equipment is confined to the main electrical room, which is roughly 12' x 5'. 

 Tenant No. 1 was the original tenant in the building and had a 400-amp distribution system that was fed from the existing CT/Term can that we did not want to touch.
 Tenant No. 2 required an 800-amp service; so we had a second 400-amp service brought into the room from the same TEP transformer and had an additional 400-amp CT/Term can installed next to the 800-amp to isolate Tenant No. 1’s service. We then took Tenant No. 1’s load off the 800-service and isolated it to the new 400-amp.
The 400-amp service was constructed by bringing into the room a 4" conduit 2 ft above floor level where it was then extended vertically 7 ft towards the roof, and then 6 ft horizontally along the wall towards the new service can, where it was then brought down 4 ft to the top of the new CT/Term can.

The inspector feels that under NEC 230.70(1) too much of the service is exposed, and that the new CT can could have been placed closer to the point of entrance. The new location required the relocation of smaller equipment not related to Tenant No. 2, which was ultimately moved due to the existing fire protection riser. Had the contractor located the new service can there, it would have reduced the nearest point of entrance by 13 ft (due to the conduits running up to the structure then back down to the new service equipment).

The services are energized and both tenants are operational.

We feel that since the Code does not delineate a maximum distance and leaves the decision up to the AHJ, the distance is subject to the official’s interpretation as to what exactly may have been the “nearest point of entrance” in an existing electrical room, especially with the existing conditions at hand. At this point, the service equipment and feeders could be rearranged to make the exposed runs shorter but the fact remains that we would still have 4 ft of exposed conduits.
 Attached is a rough sketch for your assessment. —S. P.

Answer 7. Before I actually attempt to address the submitter’s concerns, I think we need to establish a common understanding of the issues. As I understand this installation, two tenant spaces were being developed from a building with an existing 800-ampere service providing for one tenant space (Tenant Space No. 1) and a house meter. Tenant Space No. 1 was supplied through an existing 400-ampere service disconnecting means that was located in the north end of the electric room. Tenant Space No. 2 required a supply with an 800-ampere capacity so the existing service-entrance conductors were utilized for Tenant No. 2 and a new 400-ampere service lateral was run to the electric room to feed the existing 400-ampere disconnecting means for Tenant No. 1.

The new service conductors enter the electric room on the same end as the fire protection riser (south end) and were run to the north end of the electric room to a new 400-ampere CT cabinet, and then to the existing 400-ampere disconnect switch. Additional information obtained from the submitter indicated that there was sufficient working clearance and headroom to accommodate the new 400-ampere CT cabinet and the 400-ampere disconnecting means at the south end of the electric room. The electric room was not constructed as a vault. For now, we will assume the installation is customer-owned and therefore covered by the NEC.

The main concern of the submitter is with the application of the terms readily accessible location and nearest the point of entrance. In my opinion, the reasons for the use of these two terms is to make sure the service disconnecting means can be reached quickly for operation and that we have the shortest possible length of unprotected conductors (without ground-fault and short-circuit protection) inside a building or structure.

Section 230.70 requires that a means be provided to disconnect all the conductors in a building or structure from the service-entrance conductors. Section 230.70(A) tells us to locate the service disconnecting means in accordance with 230.70(A)(1), (A)(2) and (A)(3). Section 230.70(A)(1) requires the service disconnecting means to be installed at a readily accessible location either outside a building or structure or inside, nearest the point of entrance of the service conductors.

In analyzing 230.70(A)(1), we find there are two basic requirements. First, whether the service disconnecting means is located outside or inside a building or structure, it must be readily accessible. This means that the disconnecting means must be capable of being reached quickly without one having to climb over, or remove obstacles or resort to the use of a portable ladder (see Accessible, Readily in Article 100). Second, when the service disconnecting means is located inside a building or structure, it is required to be located nearest the point of entry of the service conductors. I have always found it interesting that this is a rule about the disconnecting means, but its intent is to limit the length of the service conductors.

Without considering 230.6 regarding conductors considered outside the building, the nearest readily accessible location for the 400-ampere service disconnecting means for Tenant Space No. 1 would be at the south end of the electric room. However, in accordance with 230.6(2) and (3) respectively, if the 4" conduit were encased in concrete or brick not less than 2" thick within the electric room, or if the electric room was a vault meeting the construction requirements of Article 450 Part III, the 400-ampere service disconnecting means could have been located at the north end of the electric room.

I agree with the submitter that the NEC assigns the responsibility for interpreting the Code to the authority having jurisdiction. This is especially true where parts of the installation are exiting and/or there are no hard-and-fast measurements specified. In these cases, much is left to the discretion of the AHJ.

In my opinion, the requirement for a service disconnecting means installed inside a building or structure to be at a “readily accessible location, nearest the point of entrance of the service conductors” has always meant the disconnecting means must be installed at the first point inside the building or structure that has sufficient working clearances and headroom so that one does not have to climb over something or use a portable ladder to reach it. This location is intended to be the one that results in the shortest length of conductors.

Now that we have discussed the main concern of the submitter—the application of the terms readily accessible and nearest the point of entry, let us consider another issue. As with many existing installations, the actual circumstances can present significant and unique challenges for the AHJ as well as installers and designers. In this case, the submitter noted in his inquiry that the service-entrance conductors had already been energized. Further telephone correspondence with the submitter established that by the time all these issues became known the utility company had already taken over ownership of these conductors before the inspector had looked at them.

Unless the installation is being made by the utility and the conductors are terminating in utility-owned equipment, the installation is not under the exclusive control of the utility company at the time it is installed and the NEC applies (see 90.2 (B) (5)). There are many cases where the installation is not made by the utility but it will assume ownership once the system is completed, hopefully inspected and approved by the AHJ, and energized. In these cases, the installation must meet the requirements of the National Electrical Code. Significant challenges in obtaining compliance can be expected if the equipment becomes energized prior to inspection and approval by the AHJ, and if the utility has taken over ownership. We will leave that discussion for future issues of IAEI News, but I felt it was worth mentioning. — Mark R. Hilbert, CMP-4
(November/December 2007)

| Return to top |


The views of the authors of Focus on the Code and the editor are provided solely as a public service. 

The views expressed are not the official position of NFPA, the NEC Correlating Committee or any of its panels, IAEI, IAEI News, or the author's employers. Nor are they intended to represent a formal or informal interpretation of the NEC

 

 

Get Focused!

Articles 90, 100, 110, Annex A, Annex G
Articles 210, 215, 220, Annex D, Examples 1-6
Articles 300, 590, 720, 725, 760, Chapter 9, Tables 11(a) and (b), Tables 12(a) and (b)
Articles 225, 230
Articles 200, 250, 280, 285
Articles 310, 400, 402, Chapter 9 Tables 5 through 9, Annex B
Articles 320, 322, 324, 326, 328, 330, 332, 334, 336, 338, 340, 382, 394, 396, 398
Articles 342, 344, 348, 350, 352, 353, 354, 356, 358, 360, 362, 366, 368, 370, 372, 374, 376, 378, 380, 384, 386, 388, 390, 392, Chapter 9 Tables 1-4, Annex C
Articles 312, 314, 404, 408, 450, 490
Articles 240, 780
Articles 409, 430, 440, 460, 470, Annex D, Example D8
Articles 610, 620, 625, 630, 640, 645, 647, 650, 660, 665, 668, 669, 670, 685, Annex D, Examples D9 through D10
CMP-13
Articles 445, 455, 480, 490, 690, 692, 695, 700, 701, 702, 705
Articles 500, 501, 502, 503, 504, 505, 506, 510, 511, 513, 514, 515, 516
Articles 517, 518, 520, 525, 530, 540
Articles 770, 800, 810, 820, 830
Articles 422, 424, 426, 427, 680, 682
Articles 406, 410, 411, 600, 605
Articles 545, 547, 550, 551, 552, 553, 555, 604, 675, Annex D, Examples D11 and D12
CMP-20 (Pre-2005 Code)
 
 

Home  | Join | Advertising | Seminars | Contact Us | Privacy Statement | Legal Notices
Copyright © 2006 IAEI. All Rights Reserved.