|
|
||
|
IAEI News>Focus on the Code >CMP-5
Question 1. Section
250-100 contains the following statement: 'Regardless of
the voltage of the electrical system, the electrical
continuity of noncurrent-carrying metal parts of
equipment, raceways, and other enclosures in any
hazardous (classified) location as defined in Article
500 shall be ensured by any of the methods specified for
services in Section 250-94 that are approved for the
wiring method used.' Answer 1. This
question deals with the requirements for bonding in hazardous locations. It
is important to utilize the proper Code sections and have a general
working knowledge of the Code and the problem to properly apply the Code in this type of installation. While an equipment grounding conductor is
installed in the metallic raceway, the bonding requirements in Chapter 5 of
the NEC have not been satisfied based on the information and drawing
provided. The
illustration shows a light, a seal fitting, and a 4-inch square box in the
branch circuit routed to the panelboard. If the panelboard is the service,
then a bonding means in accordance with Section 250-94 is required to be
provided for all metal raceways all the way back to the service grounding
point. In the illustration, it appears as though the proper bonding methods
are not complete through all intervening raceways back to the service. The
inclusion of the equipment grounding conductor inside the raceway does not
satisfy the requirements of Sections 501-16(a), 502-16(a), 503-16(a), or
250-100. Hope this helps paint a clearer picture of the need for boning of
these metal enclosures and raceways when installed in these hazardous
(classified) locations. — Michael J. Johnston,
CMP-5 | Return
to top | Question 2. I have a separately
derived system that is feeding panel “A” that has a
feed-through on the load side of the main breaker in
panel “A” that feeds panel “B.” Panel “B” is
a main lug only panel next to panel “A.” | Return
to top | Question
3. Section
408.3(E) gives a phase arrangement for busbars. Is this
an arrangement for circuit breakers and fused
disconnects? I ask because IAEI News, January/February
2002, page 39, shows from left to right, phase A, B, and
C. Page 40, same issue, shows arrangement C, A, and B.
Page 104 of 2002 NEC Analysis also shows C, A, and B.
The diagram, on page 104 of the Analysis, does not show
the equipment grounding conductor connected directly to
the grounding conductor (same as page 40 of
January/February issue of IAEI News). — J.J. The
drawing you are referring to in the January/February
2002 edition of the IAEI News on page 39 does not
show the phase arrangement. The equipment in which the
feeder conductors terminate is required to meet the
phase arrangement required by 408.3(E). There are no
phases of the transformers or panelboards identified in
figures 3, 4, or 5 of the article. Figure 2, on page 38,
identifies the phases of the delta transformer to
indicate the voltages between the phase conductors of
that transformer, but was not intended to relate to
figures 3, 4, or 5. Based on
the NEC, phase arrangement does not apply to
circuit breakers or fused switches but is applicable to
3-phase switchboards or panelboards. If the transformer
secondary terminates in an overcurrent device in
accordance with 240.21(C)(6) and 408.16, then the phase
arrangement would be required to be A, B, C from left to
right as viewed from the front of the equipment. Figure 5
on page 40 of the IAEI News article and the
graphic on page 104 of the 2002 NEC Analysis
of Changes book do not indicate the phase
identification or arrangement simply because that was
not the emphasis of those particular drawings. It should
be noted that the phase arrangement in the panelboards
in both drawings would be required to meet the rule in
408.3(E). The
green conductor shown from the source enclosure to the
first overcurrent device enclosure in both drawings is
referred to by the Code as an equipment bonding
jumper, and is supposed to show a connection between the
transformer (source) enclosure and an equipment
grounding terminal bar within the panelboard [see
250.30(A)(5)]. Phase
arrangement of the panelboards in these drawings was not
shown, but as a requirement of the Code and
equipment standard, it would need to be as specified in
408.3(E). Typically the phase terminals or leads at the
secondary side of transformers are identified as X1, X2,
X3, and XO, and the equipment the conductors terminate
in requires the phase identification of A, B, and C. I
hope this provides some clarity relative to phase
arrangement requirements set forth in the NEC. —
Michael Johnston, CMP-5 | Return
to top | Question 4. The local
inspector has turned down my service because I took the
grounding electrode conductor to the meter can instead
of the fused disconnect. The service is a 400-amp
service built on a pole to serve a ground water cleanup
site. We installed the K meter on one side of the pole,
and the disconnect on the other side. If I understood
the Code correctly, then the grounding electrode
conductor could be connected to the grounded conductor
at any point between the service drop and the enclosure
that contained the first means of disconnect. His
contention is that the Code requires it to be in
the service equipment and that the meter is not
considered part of the service equipment. Could you help
clear this up for us? — W.J. As a general rule, the NEC would permit the connection of the grounding electrode
conductor in either of the locations mentioned in the
question: the meter or the service disconnecting means.
This is referenced in 250.24(A)(1) [NEC 2002]. Of course, this would be
acceptable unless there are local codes that prohibit
this connection from being made in meter socket
enclosures. The authority having jurisdiction (AHJ) has
the responsibility of interpreting the rules and
enforcing them at the local levels. — Michael J.
Johnston, CMP-5
| Return
to top | Question
5. I am a building inspector with the city of Noblesville,
Indiana. I have a question concerning 250.56 [NEC 2002].
May this section be applied to residential construction?
Any help that you can provide will be most appreciated. —
D.S. Answer 5. Section
250.56 of NEC 1999 and 2002 would both be
applicable to all types of construction, not just
residential. The key factor is to remember that the
25-ohm requirement is to be applied to a single
electrode of the rod, pipe, or plate type. Where the
resistance to ground is questionable, ground resistance
testing might be applied to demonstrate 25 ohms or less
on the single electrode; or an additional electrode of
the types specified in 250.52(A)(2) through (A)(7) is
required to be installed to augment the single
electrode. Where multiple electrodes are installed,
the Code requires a minimum 1.8 m (6 ft.)
separation between them. It is important to follow any
manufacturer’s installation instructions that might be
included with listed grounding electrodes. Those might
require more distance for separation than the minimum
distance given in the Code. Note that the 25-ohm
requirement is not applicable to the grounding electrode
system covered in 250.50. It is applicable to single
electrodes of the rod, pipe, or plate variety. It should also be noted that
supplementary grounding electrodes installed in
accordance with 250.54 are not required to meet the
maximum 25-ohm resistance-to-ground rule specified in
250.56. They should be connected to and supplement the
required equipment grounding conductor of the circuit.
The earth shall not be permitted as the sole equipment
grounding conductor. Additional information about
supplementary and supplemental grounding electrodes is
provided in an article on this topic in the
September/October 2002 edition of IAEI News.
Hopefully, this helps address your concerns. As always,
the authority having jurisdiction has the responsibility
for interpretation and enforcement of the applicable
electrical code(s) and any local code amendments that
may be adopted by that jurisdiction. — Michael J. Johnston, CMP-5 | Return
to top | Question
6. I am an electrical inspector,
and an IAEI member in the Central Pennsylvania Chapter. After
reading Michael J. Johnston’s article on supplementary
grounding electrode, I’m a little confused. Mr. Johnston
states that the NEC does not require a ground rod at
parking lot lights. I have been told by my managers that they
are required, because they are considered a separate
structure, and fall under 250.32(A). Could you shed some
light on this subject? Thank you. — P.S. Answer 6. Regarding
your question to supplementary grounding electrodes, while a
light pole base and the pole itself are technically structures
by definition, the NEC does not require an electrode in
these locations. Supplementary grounding electrodes overlay
the required grounding and bonding safety system. The light
pole base was just an example of one type of equipment where a
supplementary grounding electrode is often installed as an
option. There is an exception to 250.32(A) that should be
referred to in this particular case you mentioned in the
question. In accordance with the exception, a grounding
electrode is not required for a structure or building that is
supplied by a single branch circuit that includes an equipment
grounding conductor for grounding the equipment. The poles are often supplied by a branch
circuit in accordance with the exception. A metal shade screen
structure with a circuit supplying carport lighting is another
example where the exception to this requirement is often used.
Some designers or engineers actually specify a grounding
electrode at light pole standard as part of the job
specification. Other examples used in the article were
supplementary grounding electrodes installed at computer
equipment, machines, etc. The supplementary electrode
connection establishes a connection from the light pole to the
earth at that location. In the case of the light pole base,
sometimes the base itself serves very well as a natural
grounding electrode through the connection between the
concrete and rebar and the earth. The required equipment grounding conductor
must always be connected to the equipment, and the earth shall
not be permitted as the sole equipment grounding conductor.
Local amendments or interpretations may come into play in your
particular case. If your jurisdiction has chosen to require
these electrodes at all pole bases that is their decision. As
far as their being required at all light pole bases, this is
not presently a requirement of the Code as indicated by
the exception. I hope this helps you with your particular
question. Remember, the authority having jurisdiction has the
interpretation responsibility and approving authority, and
there might be local amendments or interpretations that may
need to be considered. — Michael J. Johnston, CMP-5 | Return
to top | Question
7. Why is an equipment
grounding conductor not required to be installed with the
service-entrance conductors from the utility transformer to
the service disconnecting means? — T.O. Answer
7. For grounded ac systems operating at less than
1000 volts, the Code requires the grounded (usually the
neutral) conductor to be brought to the service disconnect and
bonded to the service disconnecting means enclosure [see
250.24(B)]. The grounded conductor is routed with the phase
conductors of either a service lateral, or in the form of a
service drop for overhead services. This grounded conductor is
required to be sized not smaller than required to carry the
maximum unbalanced neutral load current in accordance with
220.22, and in no case smaller than the required grounding
electrode conductor specified in Table 250.66. Where the
service-entrance conductors are larger than 1100 kcmil copper
or 1750 kcmil aluminum, the grounded conductor (usually the
neutral) must be sized at least 12.5 percent of the circular
mil area of the largest ungrounded service-entrance phase
conductor. To answer this question
specifically, the grounded conductor is permitted for
grounding and bonding on the supply side of the service
disconnecting means as provided in 250.142(A) and serves two
primary purposes. The grounded conductor installed with the
service conductors serves to carry normal neutral current
loads to the utility source in normal operation; and in fault
conditions, it serves as the low impedance path to the source
that facilitates overcurrent device operation. Equipment
grounding conductors, on the other hand, are installed on the
load side of overcurrent protective devices with feeders and
branch circuits and are sized based on the rating of the
overcurrent protective device using Table 250.122. Hopefully
this helps address your concerns. As always, the authority
having jurisdiction has the responsibility for interpretation
and enforcement of applicable electrical code(s) and any local
code requirements that may be adopted by that jurisdiction. —
Michael J. Johnston, CMP-5 | Return
to top | Question
8. Are
standard wire nuts acceptable as connectors on grounding
conductors? I have been told that they are not and only
"greenies and crimp devices" are acceptable on
grounding conductor splices. — M. J. Answer 8. Your
question addresses the use of "wire nuts" or wire "pressure
connectors" and whether they a permitted for use to splice equipment
grounding conductors together in outlet boxes, junction boxes, and so forth.
The simple answer is yes. Wire nuts (wire pressure connectors) are permitted
for this purpose (see Section 250.8). Also take a look at Section 250.148.
Here one can find the language that indicates splices in equipment grounding
conductors shall be made in accordance with 110.14(B), except that
insulation is not required for these types of splices. This is because they
are not normally current-carrying conductors. They should only carry current
during abnormal conditions or events such as ground faults. The equipment
grounding conductors carry the ground-fault current for the time it takes an
overcurrent device to open the faulted circuit. It should be noted that the
same type of wire nut or wire pressure connector used for the ungrounded
(hot) conductors is also exposed to the ground-fault current for the time it
takes the overcurrent device to open and clear the faulted condition (see figure
1). Section 110.14(B) addresses all types of
splices for conductors and does not differentiate between
ungrounded (hot) conductors or equipment grounding conductors.
This section requires that the splice be insulated with
insulation equivalent to the insulation of the conductor. As
can be seen in 250.148, there is a modification that allows
splices in equipment grounding conductors to be uninsulated.You mentioned "greenie" or
"crimp devices" in the question. Those devices are
certainly permitted also for splicing equipment grounding
conductors if they are suitable for the use, but they are not
the only devices suitable for the use as required by the
wording of Section 250.148. The first sentence of 250.148
indicates that separate equipment grounding conductors shall
be spliced or joined within the box. This can be accomplished
with greenies, crimp sleeves, wire nuts, or other suitable
devices in accordance with 110.14(B). The color of the device
used for this purpose is not a requirement of the Code.
The last part of the first sentence indicates that the
equipment grounding conductors are required to be connected to
the box with devices suitable for the purpose. This would be a
listed grounding clip or suitable grounding screw for example
[see also Section 250.148(A)]. Remember, sheet metal screws
are not permitted to attach equipment grounding conductors to
metal boxes as prohibited by Section 250.8.Another section to keep in mind here is
Section 110.3(B). Basically this section requires equipment to
be installed and used in accordance with the installation
instructions and within the limits of the product listing.
There is also valuable information in the General Information
for Electrical Equipment, 2002 edition (UL White Book). See
category (ZMVV) on page 133. Information about grounding and
bonding equipment such as ground clamps, ground rods,
grounding bushings, grounding and bonding locknuts, etc., is
also included in the UL White Book under the category (KDER)
on page 58.I hope this answers your question and
clarifies which types of splicing devices are suitable for
splicing equipment grounding conductors. As always, consult
your local authority having jurisdiction, who has the
responsibility of enforcement and interpretation of the rules.
There may also be local amendments to the minimum requirements
covered by the National Electrical Code. Thanks again
for the question. — Michael Johnston, CMP-5 | Return
to top | Question
9. I am writing
to your office as a poll of various jurisdictions on the
subject of bonding (grounding) requirements for a raised
cellular floor. I will offer a brief description of the
system and the components and ask that you respond with
your view on the requirement. The system has: 2 ½ – 3" (finished
height) raised floor; ¾" floor panel; 1 ¾ – 2
¼" support cylinders; panels rest on 16 support
cylinders; panels are secured by a flat washer in each corner;
and the support cylinders are secured to concrete floor with
"Mastic" at each corner.The panel components are: 24" x
24" cementatious tile (cement and wood particles);
non-conductive; ¾" thick; the corner is recessed to
accept flat washer; and they are supported on a bed of 16
cylinders. The fasteners components have: ¼-20 screw and
1" flat washer. The support cylinders have: stamped sheet
metal; cylinders are approximately 2" round and 2"
high; threaded hole to receive ¼-20 screw; and are not
mechanically fastened to each other.The raised access floor is designed to be
installed in general office areas as a means of distributing
120-volt power and network cabling to private offices and
furniture stations.The void between the support cylinders and
the panel provides a path for laying in armored cables (type
MC or AC) for electrical loads and CAT5E for network cabling.
Due to the low height of the finished floor, this raised floor
is not to be used as an air handling space. Since the surface of the raised floor is
non-conductive (cement) and all electrical cabling will have a
bonding conductor (MC or AC cable), is bonding (grounding) the
sheet metal support structure necessary? If so, at what
interval? — R.G. Answer 9. In
general, there is no requirement in the NEC to bond such raised floor
metal framing structures. Sometimes the framing structure used to support
the raised flooring panels serves as a signal reference grid or is bonded to
field-installed signal reference grid. Keep in mind that signal reference
structures are a grounding and bonding enhancement often used in information
technology room installations that overlay the required minimum equipment
grounding and bonding conductors. Section 645.15 indicates that where signal
references structures (grids) are installed (which could be the framing in
some instances), they must be bonded to the equipment grounding system
provided for the information technology equipment. Note: It is really important to determine
that Article 645 is even allowed to be applied to this
situation. Article 645 of the NEC is only applicable to
information technology equipment and rooms if all of the
conditions set forth in 645.2 have been met. Signal reference grids are not a
requirement of the NEC and the signal reference grid
can be provided in a variety of forms such as the interlocked
framing of a raised floor, a rebar mesh system in the concrete
floor supporting the raised (platform) floor, a conductive
network assembled under raised floors, or even the metal
framing of a suspended ceiling grid system. Your second question relates to any
required bonding connection intervals, and is not applicable
since the bonding of the framing is not generally required by
the Code. If a bonding connection is required to the
raised floor framing in accordance with 645.15 (last
paragraph) because it is used as the signal reference
structure, then the bonding and interconnecting of the framing
used as the signal reference structure would be required to
meet the bonding requirements of Part V of Article 250. Signal
reference structures (grids) are generally a design issue, and
an enhancement that reaches beyond the minimum requirements
for grounding and bonding in accordance with the NEC minimums. I hope this helps provide some clarification. Always
verify with the local AHJ for any local code rules that might
be more restrictive than the minimum rules in the National
Electrical Code. —Michael J. Johnston, CMP-5 | Return
to top | The views of the authors of Focus on
the Code and the editor are provided solely as a public service. |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Home
| Join | Advertising | Seminars | Contact
Us | Privacy
Statement | Legal
Notices |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||