|
| |
 |
| No images. |
|
|
|

IIAEI
News>Issue Listing>November/December 2002 >The Danger of Voltage Gradients in the Aquatics Environment
| The Danger of Voltage Gradients in the Aquatics Environment |
Article 680 of NEC 2002 covers the swimming pool bonding grid that is an essential part of a safety aquatics complex. |
|

Hidden beneath the glamour and excitement of an
aquatics complex is a detailed
and essential safety system. This frequently
misunderstood network is the swimming pool bonding grid.
Article 680 of NEC 2002 covers this system and was
revised in this latest edition. Several sections changed
paragraph numbers and other information was reformatted
to provide clearer interpretation of this section.
Section 680.26, Bonding, was formerly 680.22 in NEC 1999. The intent of this section still remains to
provide an equipotential plane in the aquatics
environment for safety.
Why the Concern
or Need for 680.26 on Bonding?
The answer to this question can best be explained with a
real life case scenario. A lifeguard in the Kansas City
area was recently frozen to her stand and unable to move
or call out for help when a voltage gradient was
introduced into the aquatics complex she was guarding.
Here’s what happened.
The pool was in operation in early June. It was hot and
humid. A construction company was in the process of
digging trenches immediately adjacent to the pool when a
trackhoe operator ran his boom into an overhead utility
power line. The voltage of the system was 12,470 volts
phase-to-phase and 7,200 volts to ground. This large
piece of metal equipment conducted the voltage of the
utility line down to the earth adjacent to the pool,
energizing the ground with a substantial voltage
gradient. This gradient began seeking out the lowest
ground plane to be dissipated. Think of water running
down hill. Electricity, like water, seeks the lowest
point in the system. The large community pool, filled
with conductive ionic water and constructed of large
quantities of reinforcement steel, provided a major
ground plane. The gradient from the utility line,
through the trackhoe and into the earth began migrating
to the pool. The lifeguard stand was located in a direct
path between the gradient and the pool ground plane.
Immediately, the voltage gradient froze the lifeguard
when a touch potential developed between the two
stainless steel (conductive) arms of her lifeguard
stand. The current developed exceeded the let-go
threshold through her body, and she was unable to move
out of this dangerous situation. Simultaneously, the
trackhoe operator noticed that his co-worker, who was in
the pit below the trackhoe, was also appeared to be
experiencing electrical shock. He was shaking as his
hands were touching the earth on the side of the pit.
Upon seeing his co-worker in this condition, the
trackhoe operator lowered his boom. Pool patrons heard
an arc when the boom broke contact with the energized
utility line, freeing both the lifeguard and the
co-worker.
Why the Lifeguard Was Shocked
An ensuing test showed that one metal arm of the
lifeguard’s stand was tied (or bonded) to the pool
bonding grid. The other arm was floating or isolated
(not on the grid) but in contact with the earth under
the lifeguard stand. This is a violation of the bonding
requirements of NEC 680.26. This floating or isolated
arm began picking up the voltage gradient introduced by
the adjoining utility line and trackhoe. The other
bonded arm of the stand provided a ground return that
allowed current to flow through her body. (Note:
Lifeguards are constantly applying sunscreen and are
often wet with perspiration while performing their jobs.
This environment adds to a lower resistive contact with
the metal surfaces they frequently touch around the
pool.)
What Would Have Prevented this Occurrence
Had the lifeguard stand been bonded together (connected
with a low impedance) per 680.26, both arms on the stand
would be maintained at the same voltage potential. The
gradient would have still entered the pool, but as the
stand began to elevate in potential it would have done
so equally on both sides. As a result, the lifeguard
would have been protected and probably unaware of any
danger. An analogy is a squirrel running along an
overhead power line. The front feet and back feet of the
squirrel are at 12,470 volts each. Since both sets of
feet are at the same potential and there is no return
ground path, there is no net flow of current. The
squirrel is safe.
How Does the Electrical
Community Apply This Article to Assure a Safe System?
Electrical inspectors, contractors, and engineers are
faced with how to interpret this section. The engineer
must design a proper bonding grid that meets the minimum
requirements of the Code. The electrical
contractor/installer must set up this grid using proper
bonding materials and methods. And the electrical
inspector has the tough job of inspecting this grid to
ensure that it has been designed and installed according
to the NEC. Since this system is passive in nature, only
operating when a voltage gradient is present, it is
often designed, installed and inspected improperly.
After conducting over twenty bonding surveys for new and
existing aquatic complexes, I have come to several
conclusions. Let’s first start by reviewing the
minimum requirements in the NEC.
A Closer Look at the NEC?
Section 680.26(B) outlines the items that are required
to be bonded together. These include: (1) metallic
structural components, (2) underwater lighting, (3)
metal fittings, (4) electrical equipment, and (5) metal
wiring methods and equipment. My experience shows that
section (5) is often the problem area. This section
requires the following metal components to be bonded to
the bonding grid: metal sheathed cables, raceways,
pipes, and all other metal parts within the following
distances of the pool:
(1) Within 1.5 m (5 ft) horizontally of the inside pool
wall
(2) Within 3.7 m (12 ft) vertically above the pool or
observation stands, towers, platforms, or any diving
structure
Many of these items are either missed during the
original construction or compromised by future work done
around the pool.
Experience Can Teach Us How to
Inspect
Three major situations occur that cause violations in
this section. These include (1) not bonding all parts or
sections of a piece of equipment that is within five
feet of the inside pool wall during original
construction, (2) adding or moving items to the pool
after the original construction and/or (3) cutting or
repairing the pool deck.
Bond All Parts of the Equipment
The first situation that compromises safety is not
bonding all parts of a pool piece of equipment during
the original construction. An entry/exit ladder within a
pool normally requires two anchor sockets embedded
within the concrete deck to anchor the ladder. Many
ladders today have stainless handrails with plastic
steps. The two handrails are electrically isolated
because of the plastic steps. Many contractors will only
bond one anchor socket for each ladder. An inspector
sees the bonding conductor present at the handrail and
connected to one handrail and assumes the whole assembly
is bonded. The result may leave one handrail bonded to
the grid and another floating to pick a voltage
gradient. This is a touch potential shock situation
waiting to happen. The solution (and the rule) is to
require every anchor point to be bonded around the pool
deck. This applies to handrails, ladders, lifeguard
stands, canopies, and so forth. (Note: items that are
bonded with lugs not labeled and listed for the
chlorinated environment will often deteriorate and cause
a failure in the bond connection [see 680.26(C)]. These
connections should be suitable for the purpose.
Adding Amenities After the
Original Construction
The second situation is when items are added or moved.
It is common for a pool to have lifeguard stands
installed when the pool is built. At a later date, when
more money becomes available, many pools will have
accessory items such as lifeguard canopies (sunshade
covers for the guards) added to the pool. These are
generally installed by core drilling a hole into the
deck and grouting the canopy support pole in the hole. I
have yet to find any of these added canopies bonded to
the grid. It is an added expense and requires extra work
and knowledge to run a copper bonding conductor to a
grid tie point. I have also seen cases where the core
drilling will actually sever the bonding conductor
running around the pool. This causes major breaches in
the bonding grid. A solution is to have an electrical
inspection to assure that these new items are added to
the grid when a permit is pulled. Canopies are but one
example of the many items that can be added or moved
around any pool.
Cutting or Repairing the Pool
Deck
It is common to see major sections of the concrete deck
cut and replaced around a pool complex. These cuts are
usually required to repair buried water leaks, add new
piping, repair crumbling concrete, and so forth. A high
majority of this activity will sever the bonding
conductor around the pool. Remember, the bonding grid is
a passive system that only functions and carries current
when voltage gradients enter the complex. When cut,
there are no pyrotechtronics, flashover, explosion, or
overcurrent protection device operating. The person
cutting the deck will usually see the 8 AWG or larger
bare copper conductor (as required by Code) embedded in
the concrete and think, "must have been a scrape
piece of copper just laying in the concrete when the
deck was poured." I have yet to see a new bonding
conductor added to replace the one that was cut. The
result is a breached bonding system.
The Solution for Safety
How can the engineer/designer, contractor, owner, and
inspector make sure this passive bonding system is
installed correctly and maintained? Each party working
in this environment must be familiar and trained on the
requirements of 680.26. The contractor should tie every
metallic part within five feet of the inside walls of
the pool to the common bonding grid. This must be done
with clamps, pressure connectors, or exothermic welding
suitable for the purpose as outlined in 680.26(C) and
also covered in 110.3(B). The bonding methods and
materials must be approved for the aquatics environment
(see 100.11). The only suitable materials per Code are
copper, brass, copper alloys, and stainless steel. Steel
items deteriorate quickly around chlorinated water and
are not acceptable. Inspectors should view the bonding
system at several points in time during its
installation. Bonding conductors and connections must be
looked at before the concrete decking is installed and
covers these items. All items in the installation should
be labeled and listed for this environment. Filter
houses need to be viewed as well. All circulating pump
motors need to be connected to the bonding grid unless
double insulated. An ohmmeter is helpful to assure the
bonding is done at a low impedance level. A reading of
under 2 ohms should be present between all required
items. (Ed. note: This is a recommendation of the author
and not a provision of the Code. Even though this is a
good value to shoot for, there is nothing mentioned in
the Code about required testing or maximum resistance
values between metallic parts of the common bonding
grid.)
Third Party Certification of
Bonding Grid
Because of the complexity and passive nature of the
bonding grid, some consulting engineers are requiring a
third party to come in and inspect, test, and certify
that the aquatics complex bonding grid has been
installed per specifications. This certification occurs
before the aquatics complex is allowed to open. This
final stage can assure that this passive system is
completely intact as designed and functioning to provide
a degree of safety to the patrons and employees at the
local pool.
The Final Word
Nothing can substitute for training and experience.
Those designing, installing, and inspecting aquatic
parks, pools and similar installations must be familiar
with Article 680. Detailed requirements are included in
this article on all facets of electrical installations
in this environment. Proper design, installation,
inspection, and certification of the pool bonding grid
system can assure that the swimming experience at the
pool is both refreshing and safe.
Bob Herzig, P.E., is the principal of Bob Herzig and
Associates, Inc., a consulting engineer firm in the
Kansas City area that specializes in the electrical
systems associated with swimming pools and fountains.
His company designs, tests, repairs, and certifies
electrical system in all types of aquatics environments.
He has a BSEE degree from the University of Missouri at
Rolla and an MBA from Rockhurst University. He is a
registered professional engineer in seven states and
conducts seminars on electrical safety in the aquatics
environment. He currently sits on the board of directors
for the MO/KS local IAEI Chapter and the Electric League
of Missouri and Kansas and has taught power system
design classes at the University of Kansas. He can be
reached at his office at 816-420-8700 or at bherzig@kc.rr.com .
|
|
|