
IAEI
News>Issue Listing>November/December 2003 >Three Chiefs Come Full Circle on Parallel Paths and End on a Tangent
| Three Chiefs Come Full Circle on Parallel Paths and End on a Tangent |
Proper grounding and bonding are critical elements in a safe electrical installation. All inspectors and installers are encouraged to review the "new" Article 250 and become familiar with the significant changes. |
|
| by Xen George Anchales, Tom Trainor, and Connie Golovko |

NEC AND FIELD PROBLEM
Prior to the 1999 edition of the National Electrical
Code, Section 250-24(a), Two or More Buildings or
Structures Supplied from a Common Service, basically
required a feeder from the first building to be treated
as service-entrance conductors at the second building.
The neutral conductor was required to be bonded to the
building disconnect enclosure and grounded to a
grounding electrode no matter what type of wiring method
was used.
When installed this way, any metal
piping common to both buildings and bonded into the
grounding system of both buildings became a parallel
path and would carry a large percentage of the neutral
current under normal operating conditions. If someone
got in series with these paths they could possibly be
seriously shocked or electrocuted.
NEC Correction
We published articles addressing and
substantiating this problem.1 The results of those articles brought about code change
proposals, which reversed the Code requirements.
With the 1999 edition, the NEC no longer requires
one to reground the neutral conductor at the second
building. Now, the main requirement is to isolate the
neutral at the second building; only under limited
conditions can you reground it.
NEC Current Requirements
Let’s review how to properly install a subpanel. All
examples and illustrated wiring methods are for a
120/240-volt, three-wire, single-phase system, unless
otherwise noted. All code references are to the 2002 NEC.
Unfortunately, some states, such as California, are
still using older editions of the NEC; therefore,
we have provided Table 1 for a cross reference of code
sections referred to in this article. Figures
1, 2 and 3 illustrate the requirements found in Section 250.32, Two
or More Buildings or Structures Supplied From a Common
Service.
A separate building or
structure supplied by a single branch circuit
Section 250.32(A) starts by requiring a grounding
electrode at the separate building or structure. The
exception that immediately follows exempts separate
buildings or structures that are supplied by a single
branch circuit. Figure
1 illustrates that exception. The following are key
points for this installation:
1. A grounding electrode at the separate building or structure is not required.
2. Only one branch circuit supplies
the separate building or structure.
3. The branch circuit includes an
equipment grounding conductor for bonding water and gas
pipes [see Sections 250.104(A)(3) and (B)] and for
bonding the conductive non-current-carrying parts of all
equipment.
4. A disconnecting means is required
at the separate building or structure (see Section
225.32 for orderly shutdown, lighting standards and pole
sign exceptions). The disconnecting means must be
suitable for use as service equipment. However, figure
1 shows the exception to this requirement, which
would allow a snap switch as the disconnecting means for
garages and outbuildings on residential properties (see
Section 225.36 Exception).
Subpanel located in or on a building
or structure separate from the service equipment
Section 250.32(B), Grounded Systems, contains provisions
which result in two different ways to connect grounding
and bonding conductors at a subpanel located in or on a
building or structure supplied from a separate building or structure. Figure
2 illustrates 250.32(B)(1), the first way to wire a
subpanel. The following are key points for this
installation:
1. The subpanel is located in or on a
building or structure supplied from a separate building
or structure.
2. The subpanel is supplied by a
three-wire plus ground feeder (two ungrounded (hot)
conductors, one grounded [neutral] conductor and one
equipment grounding conductor).
3. The neutral bus is isolated from
the subpanel by insulating material.
4. A grounding electrode is required.
Existing electrodes must be bonded to the equipment
grounding terminal bar by a grounding electrode
conductor sized according to Table 250.66 and based on
the largest ungrounded (hot) conductor of the feeder
(note the change from the 1999 NEC, where Table
250-122 was referenced).
5. Water and gas pipes are also
required to be bonded to the equipment grounding
terminal bar. See Sections 250-104(A)(3) and (B) for the
bonding conductor size.
Figure
3 illustrates the second way to wire a subpanel. The
following are key points for this installation:
1. The subpanel is located in or on a
building or structure supplied from a separate building
or structure.
2. The subpanel is supplied by a three-wire
feeder (two ungrounded [hot] conductors and one
grounded [neutral] conductor). An equipment grounding
conductor is not run with the feeder.
3. There are no continuous metallic
paths bonded to the grounding system in both buildings
or structures involved (no parallel neutral paths, i.e.,
water pipes, gas pipes, metal raceways, and so forth).
4. Ground-fault protection of
equipment has not been installed on the common AC
service.
5. The neutral bus is bonded to the
subpanel equipment grounding bus and enclosure (like the
service equipment) and to the grounding electrode(s) and
shall be used for grounding or bonding of equipment,
structures, or frames required to be grounded or bonded.
6. A grounding electrode system is
required (just as it is for the service equipment), and
the grounding electrode is connected to the neutral bus
by a grounding electrode conductor sized according to
Table 250.66 and based on the largest ungrounded (hot)
conductor of the feeder. (Again, note the change from
the 1999 NEC, where Table 250-122 was
referenced.)
7. Water and gas pipes are required
to be bonded to the neutral bus. See Sections
250.104(A)(3) and (B) for the bonding conductor size.
Parallel neutral paths for current
may also exist from subpanels incorrectly installed in
or on the same building or structure as the
service equipment. Let’s also review how to install
these panels.
Subpanel located in or on the same building or structure as the service equipment.
Sections 250.24(A)(5) and 408.20 limit the installation
of subpanels to one method when the panel is located in
or on the same building or structure as the
service equipment. Figure
4 illustrates the only grounding and bonding
connections allowed in this situation. Remember the
following key points for this installation:
1. The subpanel is located in or on
the same building or structure as the service
equipment.
2. The subpanel is supplied by a three-wire
plus ground feeder (two hots, one neutral and one
equipment grounding conductor). Metal conduit may act as
the equipment grounding conductor when not prohibited,
such as in Section 680.25, which contains requirements
for a subpanel supplying swimming pool equipment.
3. The neutral bus is isolated from
the subpanel by insulating material (plastic, and so
forth).
4. No electrode is required at the
subpanel location.
FIELD
CORRECTIONS
Recommendations to eliminate parallel
neutral paths and to correct improperly installed
subpanels
Thousands of existing subpanel installations have the
problem of parallel neutral paths. We have come full
circle with this problem (first by addressing the Code problem and now the field problem). We will now try to
solve the issue of what to do with these existing
installations. Remember, all corrective measures must
first be approved by the authority having jurisdiction
(local electrical inspector) in your area before you
start.
The first existing installation is as
follows:
Existing Field Conditions
1. The subpanel is located in a separate building.
2. The subpanel is supplied by a three-wire
plus ground feeder (two hots, one neutral and one
equipment grounding conductor).
3. The subpanel has a neutral bus
that can be isolated.
4. The neutral conductors, the
equipment grounding conductors and the subpanel’s
grounding electrode conductor all terminate on the
neutral bus, which is bonded (by a screw or strap) to
the panel enclosure.
5. The feeder raceway is metal.
6. The water and gas pipes are not
bonded.
Field Problems
This existing installation does not meet the
requirements of Section 250.32 for the following
reasons:
1. The feeder’s metal raceway,
equipment grounding conductor and the subpanel’s
grounding electrode are all parallel neutral paths that
need to be eliminated.
2. The water and gas pipes are not
connected to the electrical supply in a manner that
establishes an effective ground-fault current path.
Recommended Corrections
1. Turn off the power to the subpanel.
2. Disconnect the bonding screw or
strap that bonds the neutral bus to the subpanel
enclosure. The neutral bus is now isolated from the
subpanel enclosure.
3. Remove all equipment grounding
conductors and the grounding electrode conductor from
the neutral bus. Only grounded (neutral) conductors are
to remain connected to the neutral bus.
4. Install an equipment grounding
terminal bar (see the panel’s label or installation
instructions for the recommended type of grounding bar
and its mounting instructions). When installed
correctly, this grounding bar will be attached (bonded)
directly to the subpanel’s enclosure.
5. The water and gas pipes are
required to be bonded to the equipment grounding
terminal bar. See Sections 250.104(A)(3) and (B) for the
bonding conductor size.
6. All equipment grounding conductors
and the grounding electrode conductor are required to be
connected to the equipment grounding terminal bar.
7. Turn the subpanel’s power back
on.
Problem Solved
The parallel neutral current paths have been eliminated
from the metal raceway, equipment grounding conductor
and the grounding electrode. The water and gas pipes are
bonded back to the electrical supply and now have an
effective ground-fault current path that will facilitate
the operation of the overcurrent device should a ground
fault to the piping occur.
Our second existing installation is
as follows:
Existing Field Conditions
1. The subpanel is located in a separate building.
2. The subpanel is supplied by a
three-wire feeder ( two hots and one neutral).
3. There are continuous metallic
paths (water and gas pipes) bonded to the neutral bus in
both buildings or structures involved.
4. Ground-fault protection of
equipment has not been installed on the common AC
service.
5. The neutral bus is bonded to the
subpanel enclosure (by a screw or strap) and is also
acting as the equipment grounding terminal bar.
6. There are no grounding electrodes
connected to the subpanel.
7. The subpanel feeder is in PVC
electrical conduit.
Field Problems
1. The water and gas pipes are
parallel neutral paths.
2. There is no grounding electrode
connected to the subpanel.
Recommended Corrections
1. Turn off the service power.
2. Pull an equipment grounding
conductor with the subpanel’s feeder.
3. Disconnect the bonding screw or
strap that bonds the neutral bus to the subpanel
enclosure. The neutral bus is now isolated from the
subpanel enclosure. Disconnect all equipment grounding
and bonding conductors.
4. Install an equipment grounding
terminal bar and connect all equipment grounding
conductors to it.
5. Install a ground rod and connect
it with a grounding electrode conductor to the equipment
grounding terminal bar.
6. The water and gas pipes are to be
bonded to the equipment grounding terminal bar. See
Sections 250.104(A)(3) and (B) for the bonding conductor
size.
7. Turn on the service power.
Problem Solved
The parallel neutral current paths
have been eliminated from the water and gas pipes. The
equipment grounding and bonding conductors have been
removed from the neutral bus and attached to an
equipment grounding terminal bar, along with the ground
rod via the grounding electrode conductor. The neutral
bus has been isolated from the subpanel enclosure.
Our last existing installation
involving a subpanel is as follows:
Existing Field Condition
1. The subpanel is located in the same building as the service equipment.
2. The subpanel is supplied by a three-wire
feeder in flexible metal (steel) conduit, over 1.8 m
(6 ft) long and not listed for grounding.
3. There is no equipment grounding
conductor with the feeder supplying the subpanel.
4. There is no equipment grounding
terminal bar, grounded conductors (neutrals) and
equipment grounding conductors are all connected to the
neutral bus, which is bonded to the subpanel enclosure.
Recommended Corrections
1. Turn the service power off.
2. Pull an equipment grounding
conductor with the feeder supplying the subpanel.
3. Disconnect the bonding screw or
strap that bonds the neutral bus to the subpanel
enclosure. The neutral bus is now isolated from the
subpanel enclosure. Remove all equipment grounding
conductors.
4. Install an equipment grounding
terminal bar and connect all equipment grounding
conductors to it.
5. Turn on the service power.
Problem Solved
The parallel neutral current path has
been eliminated from the flexible metal conduit. The
equipment grounding and bonding conductors have been
removed from the neutral bus and attached to an
equipment grounding terminal bar along with the new
equipment grounding conductor pulled with the feeders.
The neutral bus has been isolated from the subpanel
enclosure.
OTHER
PARALLEL NEUTRAL PATHS
Our focus on neutral current on multiple paths has
primarily been between services and subpanels. However,
objectionable current on the grounding and bonding paths
and other metal parts may be created from other improper
connections between neutral and ground or grounded metal
enclosures. We will now discuss two common situations
where parallel paths for normal neutral current are also
created.
Non-Separately Derived Systems—Transformers
and Generators
Our first example will cover non-separately
derived systems such as an emergency or standby
generator. On non-separately derived grounded systems
(example: a 480Y/277V system with a three-pole transfer
switch where the neutral is carried through solid)
common installation errors, code violations and various
grounding schemes can create parallel paths for neutral
currents over grounding and bonding paths. This would be
in violation of Section 250.6, Objectionable Current
Over Grounding Conductors.
Parallel Neutral Paths
Many times generators are shipped
from factories with their neutrals bonded to their case.
If the generator is connected through a transfer switch
which does not open the service supplied system neutral
(as in the example above), the generator’s ground and
neutral conductors, which are bonded together at the
generator, will establish parallel neutral paths through
the grounding conductor, interconnecting metal raceway
and the generator’s electrode.
Recommended Corrections
The recommended correction in this
case would be to isolate the neutral at the generator
from the case, grounding conductors and electrodes. The
neutral is also isolated from the transfer switch
enclosure; however, it is bonded to the service
equipment enclosure, in addition to being grounded there
(see figure
5).
Separately Derived Systems—Transformers
and Generators
Our second example will cover separately
derived grounded systems which include transformers
and generators. In the case of our 480Y/277V system used
above, it is now connected through a four-pole transfer
switch where the neutral is switched open. The neutral
from the generator and the neutral at the service are
now isolated from each other. The neutral is also
isolated from the transfer switch enclosure (see figure
6).
Code Requirement To Prevent Parallel
Neutral Paths
Requirements for grounding a
separately derived AC system are located in Section
250.30. Simply put, this section requires bonding and
grounding connections either at the transformer or
generator, or at the first (fused) switch or circuit
breaker they feed, but not at both (see Section
250.30(A)(1) Exception 1), for that would establish a
parallel neutral path on the grounding and bonding paths
between them (see figure
7).
CONCLUSION
We have pointed out the problems of
neutral current on parallel paths in previously
published articles. Those articles helped to change the Code in order to prevent those problems from occurring in new
installations. This article illustrates these changes
and also tells you how to fix the problems in existing
installations.
Now that we have come full circle, so
to speak, on the problems of parallel neutral paths,
where do we go from here? Well, here’s a tangent to
consider:
TANGENT
We do not think we can tell people
too often that they should study the Code, in
general, and Article 250, in particular. Article 250 has
undergone significant revision in both the 1999 and 2002
editions of the NEC. The intent of these changes
was to make the article easier to read and understand.
The changes to Section 250.32 as illustrated above were
only one of many.
One of the more important changes was
the addition of Article 250.4 (250-2 in the 1999
edition), which provides performance requirements for
grounding and bonding. Performance requirements are
helpful since they actually define what grounding and
bonding are intended to accomplish in the electrical
system.
Article 250 now clearly states that
grounding performs a specific function in the electrical
system and that bonding performs a separate and
distinctly different function. The 1999 NEC introduced the term fault-current path to better
describe the necessary function performed by bonding.
The 2002 NEC adds definitions of ground-fault, ground-fault current path and effective
ground-fault current path. These definitions, in
conjunction with the performance requirements, help to
explain the "why" of grounding and bonding
requirements.
Proper grounding and bonding are
critical elements in a safe electrical installation. All
inspectors and installers are encouraged to review the
"new" Article 250 and become familiar with the
significant changes. We also recommend IAEI’s Soares
Book on Grounding for further study on this
important topic.
1 "Subpanels: Special Wiring and Grounding
Requirements," 1993 Sept./Oct. Building Standards
Magazine and the Building Official and Code
Administrator Magazine, Sept./Oct. 1994; "A
Question of Current—Objectionable or Not," IAEI
News, May/June 1996; and a follow-up article by Tom
Trainor, "A Question of Current—or Code
Interpretation?" IAEI News, Sept./Oct. 1996.)
Constantine S. Golovko, P.E., the
former chief electrical inspector for the county of Los
Angeles. Golovko is a registered professional electrical
engineer in California and is now fully involved in his
consulting practice. He is a past president of IAEI’s
Southwestern Section, former member of UL’s Electrical
Advisory Council, a past chairman of the NEC code-making
panel 7 and former member of the ETL Technical Advisory
Council.
Tom Trainor is the retired deputy
director of inspection services for the city of San
Diego. He was a member of NFPA, the UL Electrical
Council and the UL/IAEI Technical Advisory Panel. He
served five terms on CMP-18 and one term as chair of
CMP-7. He has been president of the Southern California
Chapter and the Southwestern Section and was IAEI
international president in 1998. He was elected as an
IAEI international honorary member in 2001.
Xen George Anchales, CBO, is
currently a senior plans examiner and former chief
electrical inspector for the county of San Bernardino.
He is an Electrical Council member for Underwriters
Laboratories, Inc., and a former member of the National
Electrical Code CMP-17, a visiting lecturer at the
University of California Riverside. He retired from San
Bernardino Valley College where he taught the Uniform
Building, Plumbing, Mechanical and National Electrical
codes.
|